3.5.3 Major Subdivision, No New Streets or Public Improvements/Infrastructure Flow Chart
Major Subdivisions that do not create any new streets require the following steps as outline as outlined in Section 3.2. A process flow chart for this type of subdivision is included below.
- Pre-Application Meeting (See section 3.2.1)
- Project Neighborhood Participation Program (See Section 3.2.2)
- Application Submittal (See Section 3.2.3)
- Completeness Review (See Section 3.2.4)
- Agency Review (See Section 3.2.5)
- Public Notice (See Section 3.2.7)
- City Planning Commission Approval (See Section 3.2.8)
- Final Subdivision Plan Approval (See Section 3.2.11)
- Recordation of Approved Subdivision Plan (See Section 3.2.12)